Kingsland Road Bridge Closure

Replacement of Kingsland Road Bridge (No. 1600-081) over the Third River in the City of Clifton:

This project includes the complete replacement of the existing Kingsland Road Bridge No. 1600-081 over Third River. 

The bridge is located near the Clifton / Nutley border.  The bridge span is approximately 30’.  The project also includes roadway reconstruction, milling and paving, new sidewalks, curbs, drainage inlets and the relocation of the sewer line and gas main.  

The original bridge was built circa 1900 and widened in 1925.  

Vehicle traffic will be detoured during construction.  Construction duration is anticipated to be 300 calendar days.  Bridge will be closed starting on Monday, July 12, 2021.